Logo Specialties manufactures, among other things, woolen blankets for the athletic teams of the two local high

Question:

Logo Specialties manufactures, among other things, woolen blankets for the athletic teams of the two local high schools. The company sews the blankets from fabric and sews on a logo patch purchased from the licensed logo store site. The teams are as follows:

Knights, with red blankets and the Knights logo

Raiders, with black blankets and the Raider logo

Also, the black blankets are slightly larger than the red blankets.

The budgeted direct-cost inputs for each product in 2012 are as follows:

image

Unit data pertaining to the direct materials for March 2012 are as follows:

image

Unit cost data for direct-cost inputs pertaining to February 2012 and March 2012 are as follows:

image

Manufacturing overhead (both variable and fixed) is allocated to each blanket on the basis of budgeted direct manufacturing labor-hours per blanket. The budgeted variable manufacturing overhead rate for March 2012 is $15 per direct manufacturing labor-hour. The budgeted fixed manufacturing overhead for March 2012 is $9,200. Both variable and fixed manufacturing overhead costs are allocated to each unit of finished goods. Data relating to finished goods inventory for March 2012 are as follows:

image

Budgeted sales for March 2012 are 120 units of the Knights blankets and 180 units of the Raiders blankets. The budgeted selling prices per unit in March 2012 are $150 for the Knights blankets and $175 for the Raiders blankets. Assume the following in your answer:Work-in-process inventories are negligible and ignored.Direct materials inventory and finished goods inventory are costed using the FIFO method.Unit costs of direct materials purchased and finished goods are constant in March 2012.Required1. Prepare the following budgets for March 2012:a. Revenues budgetb. Production budget in unitsc. Direct material usage budget and direct material purchases budgetd. Direct manufacturing labor budgete. Manufacturing overhead budgetf. Ending inventories budget (direct materials and finished goods)g. Cost of goods sold budget2. Suppose Logo Specialties decides to incorporate continuous improvement into its budgeting process. Describe two areas where it could incorporate continuous improvement into the budget schedules in requirement1.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting A Managerial Emphasis

ISBN: 978-0132109178

14th Edition

Authors: Charles T. Horngren, Srikant M.Dater, George Foster, Madhav

Question Posted: