McGee Carpet and Trim installs carpet in commercial offices. Andrea McGee has been very concerned with the amount of time

Question:

McGee Carpet and Trim installs carpet in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:

McGee Carpet and Trim installs carpet in commercial offices. And


(a) Determine the expected completion time and variance for each activity.
(b) Determine the total project completion time and the critical path for the project.
(c) Determine ES, EF, LS, LF, and slack for each activity.
(d) What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?

This problem has been solved!


Do you need an answer to a question different from the above? Ask your question!

Step by Step Answer:

Related Book For  answer-question

Operations management

ISBN: 978-0132163927

10th edition

Authors: Jay Heizer, Barry Render

View Solution
Create a free account to access the answer
Cannot find your solution?
Post a FREE question now and get an answer within minutes. * Average response time.
Question Posted: July 15, 2013 04:44:05