On February 1, 2011, Arrow Construction Company entered into a three-year

On February 1, 2011, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2011, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent and cash collected was $2,250,000.


In 2012, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2012 billings were $2,750,000 and $2,475,000 cash was collected. The project was completed in 2013 after additional costs of $3,800,000 were incurred. The company's fiscal year-end is December 31. Arrow uses the completed contract method.


Required:

1. Calculate the amount of gross profit or loss to be recognized in each of the three years.

2. Prepare journal entries for 2011 and 2012 to record the transactions described (credit various accounts for construction costs incurred).

3. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2011 and 2012.


Balance Sheet
Balance sheet is a statement of the financial position of a business that list all the assets, liabilities, and owner’s equity and shareholder’s equity at a particular point of time. A balance sheet is also called as a “statement of financial...

Members

  • Access to 2 Million+ Textbook solutions
  • Ask any question from 24/7 available
    Tutors
$9.99
VIEW SOLUTION
OR

Non-Members

Get help from Accounting Tutors
Ask questions directly from Qualified Online Accounting Tutors .
Best for online homework instance.