Refer to question 11 at the end of Chapter 6. Assume that Systems Analysis actually finished at

Question:

Refer to question 11 at the end of Chapter 6. Assume that ‘‘Systems Analysis’’ actually finished at 8 weeks, ‘‘Design Input & Output’’ actually finished at 15 weeks, and ‘‘Design Database’’ actually finished at 19 weeks. Recalculate the expected project completion time. Which Chapter 7 Schedule Control 227 activities would you focus on in order to get the project back on schedule?