Question:

The plant is to produce 3.5 × 106 kg/year of "67% Cl." Assuming that the plant operates 300 days per year, 24 hours per day, calculate the required hourly feed rates (kg/h) of the 10 wt% PVC slurry and of C12(g) to the absorber and the production rate of hydrogen chloride (kg/h) in the chlorination reactor. (Suggestion: Write balances around the system composed of the chlorine absorber and chlorination reactor.)