An Army Corps of Engineers project for improving navigation on the Ohio River will have an initial cost of $6,500,000 and annual maintenance of $130,000. Benefits for barges and paddle wheel touring boats are estimated at $820,000 per year. The project is assumed to be permanent and the discount rate is 8% per year. Determine if the Corps should proceed with the project.