In Problem 8.20, two methods of cooling water treatment are analyzed. These are revenue alternatives which generate

Question:

In Problem 8.20, two methods of cooling water treatment are analyzed. These are revenue alternatives which generate annual savings against their costs.

(a) Perform the complete procedure for incremental ROR analysis for revenue alternatives to determine which method to select at MARR = 5% per year.

(b) If a MARR of 8% per year were required, what recommendation would you make?


Data from problem 8.20

EP Electric has identified two new methods to treat its cooling water. Alternative I (for inflow) would treat the raw water with a conventional reverse osmosis system so that the cycles of concentration could be increased from 5 to 20. This will result in water cost savings of $360,000 per year and chemical cost savings of $56,000 per year. The initial cost of the equipment will be $2.3 million with an operating cost of $125,000 per year.

Alternative B (for blowdown) will treat the cooling tower blowdown water using a highpressure seawater reverse osmosis system to recover most of the water that is sent to an evaporation pond. This option will result in water savings of $270,000 per year. The cost of the system will be $1.2 million with an operating cost of $105,000 per year. Assuming one of the two methods must be installed, determine which is preferred on the basis of the incremental ROR value using MARR of 5% per year, which is a typically low return expected of government projects. Use a 10-year study period with no salvage value for either system. See Problem 8.41 for more on this situation.

Salvage Value
Salvage value is the estimated book value of an asset after depreciation is complete, based on what a company expects to receive in exchange for the asset at the end of its useful life. As such, an asset’s estimated salvage value is an important...
MARR
Minimum Acceptable Rate of Return (MARR), or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 978-0073523439

8th edition

Authors: Leland T. Blank, Anthony Tarquin

Question Posted: