King Construction Company began work on a contract in 2019.

King Construction Company began work on a contract in 2019. The contract price is $4,000,000, and King determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows:
................................................................................................2019
Costs incurred during the year .....................................$ 800,000
Estimated costs to complete, December 31 ...............2,400,000
Billings during the year ....................................................600,000
Collections during the year .............................................400,000


Required:
1. How much gross profit or loss does King recognize in 2019?
2. Next Level Prepare the appropriate sections of the 2019 income statement and ending balance sheet.

Members

  • Access to 2 Million+ Textbook solutions
  • Ask any question from 24/7 available
    Tutors
$9.99
VIEW SOLUTION

OR

Non-Members

Get help from Business Tutors
Ask questions directly from Qualified Online Business Tutors .
Best for online homework assistance.