On April 1, 2019, Pine Construction Company entered into a fixed-price contract to construct an apartment building

Question:

On April 1, 2019, Pine Construction Company entered into a fixed-price contract to construct an apartment building for $6,000,000. Pine will satisfy the performance obligations in the contract over time and appropriately accounts for this contract. Information relating to the contract is as follows:

At December 31, At December 31, 2019 2020 Percentage of completion Estimated costs at completion Gross profit recognized

What is the amount of contract costs incurred during the year ended December 31, 2020?
a. $1,200,000
b. $1,920,000
c. $1,980,000
d. $2,880,000

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting Reporting and Analysis

ISBN: 978-1337788281

3rd edition

Authors: James M. Wahlen, Jefferson P. Jones, Donald Pagach

Question Posted: