Adam Leeman Ltd has determined total factory overhead costs at both minimum and maximum levels of production

Question:

Adam Leeman Ltd has determined total factory overhead costs at both minimum and maximum levels of production — 200 000 machine hours and 300 000 machine hours respectively. The total factory overhead, made up of variable costs, mixed costs and fixed costs, was $796 000 for 300 000 machine hours and $646 000 for 200 000 machine hours. At an activity level of 200 000 machine hours, the total factory overhead consists of the following components:


Fixed costs

Variable costs

Mixed costs

$

230 000

220 000

  196 000


$

646 000


Required

A. Determine the fixed and the variable portion (rate per machine hour) of the mixed costs.

B. What should be the total factory overhead cost for 240 000 machine hours?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Accounting

ISBN: 978-1118608227

9th edition

Authors: Lew Edwards, John Medlin, Keryn Chalmers, Andreas Hellmann, Claire Beattie, Jodie Maxfield, John Hoggett

Question Posted: