On July 1, 2012, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp.

Question:

On July 1, 2012, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2014, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2012, 2013, and 2014.

Instructions
  (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2012, 2013, and 2014 (Ignore income taxes.)
  (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2012, 2013, and 2014 (Ignore income taxes.)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting

ISBN: 978-0470587287

14th Edition

Authors: kieso, weygandt and warfield.

Question Posted: