It is Monday morning, and you have just arrived at work. Complete the following MRP record as

Question:

It is Monday morning, and you have just arrived at work. Complete the following MRP record as it would appear Monday morning. Lead time is 2 weeks, and the lot size is 100.

Initial MRP 5 2 3 1 4 Week Gross Requirements Scheduled Receipts 50 70 100 40 40 80 50 Projected Available Net Requireme


During the week, the following events occur. Enter them in the MRP record.

a. The planned order for 100 in week 1 is released.

b. Thirty of the scheduled receipts for week 1 are scrapped.

c. An order for 30 is received for delivery in week 3.

d. An order for 50 is received for delivery in week 6.

e. The gross requirements of 70 in week 1 are issued.

MRP record at the end of week 1 Week 2 3 4. 5 Gross Requirements Scheduled Receipts Projected Available Net Requirements

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: