Construct a Gantt chart and network diagram for a project you are or will be involved in.
Question:
Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the activities, and construct a diagram reflecting the starting times, ending times, durations, and precedence (network diagram only) relationships among all activities. For your network diagram, use the procedure in this chapter to determine time estimates for each activity and calculate the expected time for each activity. Now determine the critical path and the early and late starting and finishing times for each activity. Which activities have slack time?