Consider the simple dependency matrix shown in Table 19.12. Which of the following statements is correct? a.
Question:
Consider the simple dependency matrix shown in Table 19.12.
Which of the following statements is correct?
a. The two activities are independent of each other and the project can carry out both of them immediately.
b. A1 is a predecessor activity to A2.
c. A2 is a predecessor activity to A1.
d. None of these statements is correct.