Refer to Problem C.13. The management of the shipping company wants to reduce the average service time

Question:

Refer to Problem C.13. The management of the shipping company wants to reduce the average service time per terminal dock to 15 minutes per truck by adding a fifth terminal dock. Assume the arrival rate of trucks and the relevant costs per hour are the same as given in Problem C.13.

1. Compute P0, Lq, Wq, Ls, and Ws for this new terminal dock waiting line system.

2. Compute the total expected cost per day for this new system, and compare it with the four-dock system in Problem C.13.


Data from problem C.13

The Gulf Shipping Company in Dubai, UAE, has four terminal docks in its warehouse. Arriving trucks form a single line and use one of the four available docks for loading and unloading of the cargo. Truck arrivals are Poisson distributed, and the average arrival rate of truck is 8 trucks per hour. The loading/unloading times of cargo have a negative exponential distribution, and the average time to load/unload a truck is 20 minutes.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: