The following jobs are waiting to be processed at Rick Carlsons machine centre. Carlsons machine centre has

Question:

The following jobs are waiting to be processed at Rick Carlson€™s machine centre. Carlson€™s machine centre has a relatively long backlog and sets freshschedules every two weeks, which do not disturb earlier schedules. Below are the jobs received during the previous two weeks. They are ready to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers.

Date Production Date Job Job Received Days Needed Job Due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 4


a) Complete the table below. (Show your supporting calculations.)
b) Which dispatching rule has the best score for flow time?
c) Which dispatching rule has the best score for utilization metric?
d) Which dispatching rule has the best score for lateness?
e) Which dispatching rule would you select? Support your decision.

Average Dispatching Flow Utilization Number Average of Jobs Lateness Job Sequence Time Metric Rule EDD SPT LPT FCFS

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Sustainability and Supply Chain Management

ISBN: 978-0133764345

2nd Canadian edition

Authors: Jay Heizer, Barry Render, Paul Griffin

Question Posted: