HiTec has just started to produce supercomputers for a limited period of 4 years. The annual demand,

Question:

HiTec has just started to produce supercomputers for a limited period of 4 years. The annual demand, D, for the new computer is described by the following distribution:

The production capacity of the plant is three computers annually at the cost of $5 million each. The actual number of computers produced per year may not equal the demand exactly. An unsold computer at the end of a year incurs $1 million in storage and maintenance costs. A loss of $2 million occurs if the delivery of a computer is delayed by 1 year. HiTec will not accept new orders beyond year 4 but will continue production in year 5 to satisfy any unfilled (backordered) demand at the end of year 4. Determine the optimal annual production schedule for HiTec.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: