Answered step by step
Verified Expert Solution
Link Copied!
Question
1 Approved Answer

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time,

image text in transcribed

image text in transcribed

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,780,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date At 12-31-2018 At 12-31-2019 At 12-31-2020 10% 60% 100% $ 372,000 $3,066,000 $5,173,000 3,348,000 2,044,000 733,000 2,430,000 4,780,000 Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Reg 1and 2 Reg 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.) Show less Year Req 1 Gross Profit (Loss) Recognized ("Upon Completion") Req 2 Gross Profit (Loss) Recognized ("Over Time") 2018 2019 2020 Total project profit (loss) $ 0 $ Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. 2018 2019 Balance Sheet (Partial) Current assets: Current liabilities: Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,780,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date At 12-31-2018 At 12-31-2019 At 12-31-2020 10% 60% 100% $ 372,000 $3,066,000 $5,173,000 3,348,000 2,044,000 733,000 2,430,000 4,780,000 Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Reg 1and 2 Reg 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.) Show less Year Req 1 Gross Profit (Loss) Recognized ("Upon Completion") Req 2 Gross Profit (Loss) Recognized ("Over Time") 2018 2019 2020 Total project profit (loss) $ 0 $ Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. 2018 2019 Balance Sheet (Partial) Current assets: Current liabilities

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Connect For Computer Accounting With Quickbooks 2021

Authors: Author

20th Edition

1264069200, 9781264069200

More Books

Students also viewed these Accounting questions

Question

Working with athletes who dope

Answered: 1 week ago