Direct costs of a project are shown on the following

Direct costs of a project are shown on the following bar chart (see Table P6.2).

Assume -> $500 per month indirect cost and 10% retainage with payment time lag of one month.

Calculate the project’s net cash flow for a 10-percent markup.

Estimate the proper markup for 1%, 1.5%, and 2% rate of return per month

TABLE P6.2 Project Bar Chart Activity Month 3 1 2 4 $2,000 $1,200 $3,000 1. Survey 2. Mobilization 3. Trench 4. Lay pipe 5. C