Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to
-
Entries and Schedules for Unfinished Jobs and Completed Jobs
Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations:
- Materials purchased on account, $3,300.
- Materials requisitioned and factory labor used:
Job No. Materials Factory Labor 101 $2,060 $1,910 102 2,510 2,580 103 1,670 1,260 104 5,640 4,740 105 3,580 3,610 106 2,620 2,290 For general factory use 700 2,830 - Factory overhead costs incurred on account, $3,930.
- Depreciation of machinery and equipment, $1,360.
- The factory overhead rate is $40 per machine hour. Machine hours used:
Job No. Machine Hours 101 17 102 18 103 22 104 67 105 19 106 18 Total 161 - Jobs completed: 101, 102, 103, and 105.
- Jobs were shipped and customers were billed as follows: Job 101, $5,580; Job 102, $6,970; Job 105, $11,050.
Required:
1. Journalize the entries to record the summarized operations. If an amount box does not require an entry, leave it blank.
Entries Description Debit Credit a. Accounts PayableCashFactory OverheadFinished GoodsMaterialsWork in Process
fill in the blank 2 fill in the blank 3 Accounts PayableCashFactory OverheadFinished GoodsMaterialsWork in Process
fill in the blank 5 fill in the blank 6 b. Accounts PayableCashCost of Goods SoldMaterialsWages PayableWork in Process
fill in the blank 8 fill in the blank 9 Accounts PayableAccounts ReceivableCashFactory OverheadMaterialsWages Payable
fill in the blank 11 fill in the blank 12 Accounts PayableAccounts ReceivableCashFactory OverheadMaterialsWork in Process
fill in the blank 14 fill in the blank 15 Accounts PayableCost of Goods SoldFactory OverheadFinished GoodsWork in ProcessWages Payable
fill in the blank 17 fill in the blank 18 c. Accounts PayableCashCost of Goods SoldFactory OverheadMaterialsWork in Process
fill in the blank 20 fill in the blank 21 Accounts PayableCashCost of Goods SoldFactory OverheadMaterialsWork in Process
fill in the blank 23 fill in the blank 24 d. Accounts PayableAccumulated Depreciation-Machinery and EquipmentCashCost of Goods SoldFactory OverheadWork in Process
fill in the blank 26 fill in the blank 27 Accounts PayableAccumulated Depreciation-Machinery and EquipmentCashFactory OverheadFinished GoodsWork in Process
fill in the blank 29 fill in the blank 30 e. Accounts PayableAccounts ReceivableCashFactory OverheadFinished GoodsWork in Process
fill in the blank 32 fill in the blank 33 Accounts PayableCashFactory OverheadFinished GoodsMaterialsWork in Process
fill in the blank 35 fill in the blank 36 f. Accounts PayableAccounts ReceivableCashFactory OverheadFinished GoodsWork in Process
fill in the blank 38 fill in the blank 39 Accounts PayableCashFactory OverheadFinished GoodsMaterialsWork in Process
fill in the blank 41 fill in the blank 42 g. Sale Accounts ReceivableCashFactory OverheadFinished GoodsSalesWork in Process
fill in the blank 44 fill in the blank 45 Accounts ReceivableCashFactory OverheadFinished GoodsSalesWork in Process
fill in the blank 47 fill in the blank 48 g. Cost Accounts ReceivableCost of Goods SoldFactory OverheadFinished GoodsSalesWork in Process
fill in the blank 50 fill in the blank 51 Accounts ReceivableCost of Goods SoldFactory OverheadFinished GoodsSalesWork in Process
fill in the blank 53 fill in the blank 54 2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process (a)(b)(c)(d)(f)(g)
fill in the blank 56 (a)(b)(c)(d)(e)(f)(g)
fill in the blank 58 (a)(c)(d)(e)(f)(g)
fill in the blank 60 Bal. fill in the blank 61 Finished Goods (a)(b)(c)(d)(e)(f)(g)
fill in the blank 63 (a)(b)(c)(d)(e)(f)(g)
fill in the blank 65 Bal. fill in the blank 66 3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Hildreth Company Schedule of Unfinished Jobs Job Direct Materials Direct Labor Factory Overhead Total No. 101No. 102No. 103No. 104No. 105
$ fill in the blank 68 $ fill in the blank 69 $ fill in the blank 70 $ fill in the blank 71 No. 101No. 102No. 103No. 105No. 106
fill in the blank 73 fill in the blank 74 fill in the blank 75 fill in the blank 76 Balance of Work in Process, April 30 $ fill in the blank 77 4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Hildreth Company Schedule of Completed Jobs Job Direct Materials Direct Labor Factory Overhead Total Finished Goods, April 30 (Job 103)Finished Goods, April 30 (Job 105)Finished Goods, April 30 (Job 106)
$ fill in the blank 79 $ fill in the blank 80 $ fill in the blank 81 $ fill in the blank 82
Check My Work2 more Check My Work uses remaining.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started