In your projectwhere, a stakeholder wants to increase the established scope. He / She estimates that this change will delay the project for a month
In your projectwhere, a stakeholder wants to increase the established scope. He / She estimates that this change will delay the project for a month days. What is the next thing you should do ?explain the answer
a. Look for alternatives that allow the compression of the schedule and thus be able to include the change.
b. Request the approval of that change to the sponsor
c. None of the above.