In your projectwhere, a stakeholder wants to increase the established scope. He / She estimates that this change will delay the project for a month

In your projectwhere, a stakeholder wants to increase the established scope. He / She estimates that this change will delay the project for a month days. What is the next thing you should do ?explain the answer

a. Look for alternatives that allow the compression of the schedule and thus be able to include the change.

b. Request the approval of that change to the sponsor

c. None of the above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Alice R. O'Grady

9th Edition

0205627730, 978-0205627738

More Books

Students also viewed these General Management questions

Question

Examine alternative approaches to behavior therapy.

Answered: 1 week ago

Question

Draw a labelled diagram of the Dicot stem.

Answered: 1 week ago

Question

=+. Alliteration The Magic of Macy's tagline.

Answered: 1 week ago

Question

=+iv. Simple promise No ordinary airline (Virgin Atlantic Airway).

Answered: 1 week ago