Products S5 and CP8 each are assigned $50.00 in indirect costs by a traditional costing system. An
Fantastic news! We've Found the answer you've been seeking!
Question:
Products S5 and CP8 each are assigned $50.00 in indirect costs by a traditional costing system. An activity analysis revealed that although production requirements are identical, S5 requires 45 minutes less setup time than CP8.
Compared to an activity-based cost system, CP8 is ________ under the traditional system.
A) undercosted
B) overcosted
C) fairly costed
D) accurately costed
E) costed the same
According to an ABC system, S5 uses a disproportionately
A) smaller amount of unit-level costs.
B) larger amount of unit-level costs.
C) smaller amount of product-sustaining costs.
D) larger amount of batch-level costs.
E) smaller amount of batch-level costs.