Question: Question 5 of 21. A significant downfall of the Milestone chart is that it does not effectively portray the relationships, dependencies, and constraints among
Question 5 of 21. A significant downfall of the Milestone chart is that it does not effectively portray the relationships, dependencies, and constraints among the project activities and events. Which schedule type was developed to combat these shortcomings? Gantt chart Resource schedule Internal schedule Network diagram Mark for follow up Back Save / Return Loter
Step by Step Solution
There are 3 Steps involved in it
Milestone charts are useful tools in project management for tracking key dates and events However they have significant limitations when it comes to d... View full answer