Question

1 Approved Answer

What is the shift capacity of a machine with the following characteristics? ---Part processing time = 70 seconds ---cutting tool has to be replace every

What is the shift capacity of a machine with the following characteristics? ---Part processing time = 70 seconds ---cutting tool has to be replace every 35 pieces and it takes 30 seconds to replace the tool ---The machine can operate 27,000 seconds per shift ---Formula: operational time per shift/(process time + set-up time/interval)

which one is correct from below :

381.04 pcs

385.71 pcs

379.39 pcs

270.00 pcs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the shift capacity of the machine we can follow the formula given which is textCapacity ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions