Which of the following characteristics is a consequence of the implementation of a plant-wide allocation rate? a)
Fantastic news! We've Found the answer you've been seeking!
Question:
Which of the following characteristics is a consequence of the implementation of a plant-wide allocation rate?
a) Allocations are first conducted among departments, and then aggregated for the plant as a whole.
b) The uniqueness of individual departments is not reflected in the cost numbers.
c) Downstream costs are not measured at all.
d) Managers have absolutely no incentive to control costs.