You and your team are estimating the duration of the coding/unit testing phase. Your optimistic estimate is
Fantastic news! We've Found the answer you've been seeking!
Question:
You and your team are estimating the duration of the coding/unit testing phase. Your optimistic estimate is 1,200 hours, and your most likely estimate is 1,700 hours, and your pessimistic estimate is 2,000 hours. The resource rate is $150 per hour. What is your cost estimate of the coding/unit test phase using the PERT estimating technique?