The following 5 overhaul jobs are waiting to be processed at Avionics Engine Repair Inc. These jobs

Question:

The following 5 overhaul jobs are waiting to be processed at Avionics€™ Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Assume that all job s arrived on day 180; today€™s date is 200.

The following 5 overhaul jobs are waiting to be processed

Using the critical ratio scheduling rule, in what sequence would the jobs be processed?