The following are the activity times for the project in Problem 12-14. Find the earliest, latest, and

Question:

The following are the activity times for the project in Problem 12-14. Find the earliest, latest, and slack times for each activity. Then find the critical path.
ACTIVITY TIME (DAYS)
A .......... 3
B .......... 7
C .......... 4
D .......... 2
E .......... 5
F .......... 6
G .......... 3