The managing partner of the Scott Corey accounting firm has decided that the system must be up

Question:

The managing partner of the Scott Corey accounting firm has decided that the system must be up and running in 16 weeks. Consequently, information about crashing the project was put together and is shown in the following table:

The managing partner of the Scott Corey accounting firm has

(a) If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? What is the total cost of this?
(b) List all the paths in this network. After the crashing in part (a) has been done, what is the time required for each path? If the project completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this byinspection.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis for Management

ISBN: 978-0132149112

11th Edition

Authors: Barry render, Ralph m. stair, Michael e. Hanna

Question Posted: