The Universal Manufacturing Company has a single assembly line that feeds two drill presses in parallel. As

Question:

The Universal Manufacturing Company has a single assembly line that feeds two drill presses in parallel. As partially completed products come off the line, they are lined up to be worked on as drill presses become available. The units arrive at the workstation (containing both presses) at the rate of 90 per hour (Poisson distributed). Each press operator can process an average of 60 units per hour (Poisson distributed). Compute L, Lq, W, and Wq.