To produce one unit of Product C requires eight hours of labor at a standard cost per

Question:

To produce one unit of Product C requires eight hours of labor at a standard cost per hour of $25.00. During the month of September, 5,500 units were produced. Actual hours and costs for the month are as follows:

Actual direct labor hours . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .41,250

Actual direct labor costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $990,000

1. Compute the actual cost per hour of direct labor for the month of September.

2. Compute the labor rate variance.

3. Compute the labor efficiency variance.


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Accounting concepts and applications

ISBN: 978-0538745482

11th Edition

Authors: Albrecht Stice, Stice Swain

Question Posted: