Bright Spark Ltd is a manufacturer of electrical switchers, and uses a standard costing system standard manufacturing

Question:

Bright Spark Ltd is a manufacturer of electrical switchers, and uses a standard costing system standard manufacturing overhead costs per switch are based on direct labour hours and are allows:

Variable overhead (5 hours @ $24 per hour) ........................................ $ 120

Fixed overhead (5 hours @ $36 per hour)* ............................................ 180

Total overhead ............................................................................ $300

* Based on capacity of 300 000 direct labour hours per month.

The following information is available for the month of October:

• 56 000 switches were produced, although 60 000 switches were budgeted.

• 275 000 direct labour hours were worked at a total cost of $7 650 000.

• Variable overhead costs were $7 020 000.

• Fixed overhead costs were $11 250 000.

Required:

Calculate the variable overhead spending and efficiency variances and the fixed overhead budget and volume variance for October. Indicate whether each variance is favourable or unfavourable?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Management Accounting

ISBN: 9781760421144

7th Edition

Authors: Kim Langfield Smith, Helen Thorne, David Alan Smith, Ronald W. Hilton

Question Posted: