Chicago Contractors got $5,400,000 contract to construct a school building for the city of Chicago. Work on
Question:
Cost incurred till Dec 21 2013........................................$1,080,000
Billings made to City...................................................$1,000,000
Amount collected from City.............................................$750,000
The estimated future cost to complete this contract is.............$3,240,000
a. Prepare Chicago Contractors 2013 Journal entries using percent of completion method
b. Show how the contract accounts will appear in the balance sheet of Chicago contractors on 12/21/2013