Davis, Inc., had the following quality costs for the years ended December 31, 2012 and 2013: At
Question:
At the end of 2012, management decided to increase its investment in control costs by 50 percent for each category's items with the expectation that failure costs would decrease by 20 percent for each item of the failure categories. Sales were $12,000,000 for both 2012 and 2013.
Required:
1. Calculate the budgeted costs for 2013, and prepare an interim quality performance report.
2. Comment on the significance of the report. How much progress has Davis made?
3. What if sales were $12,000,000 for 2012 and $15,000,000 for 2013? What adjustment to budgeted rework costs would be made? Budgeted quality audits? Assuming the actual costs for 2013 do not change, what does this adjustment say about Davis's performance?
Step by Step Answer:
Cornerstones of Cost Management
ISBN: 978-1111824402
2nd edition
Authors: Don R. Hansen, Maryanne M. Mowen