If Armer Company uses the high-low method of analysis, the equation for the relationship between hours of

Question:

If Armer Company uses the high-low method of analysis, the equation for the relationship between hours of activity and maintenance cost follows:

a. y = 400 + 9.0 x

b. y = 570 + 7.5 x

c. y = 3,600 + 400 x

d. y = 570 + 9.0 x

e. None of the above

(CMA Adapted)

Armer Company, which is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs.


Hours of ActivityMaintenance Costs


January480$4,200
February320$3,000
March400$3,600
April300$2,820
May500$4,350
June310$2,960
July320$3,030
August520$4,470
September490$4,260
October470$4,050
November350$3,300
December340$3,160
Sum4,800$43,200
Average400$3,600












Average cost per hour ($43,200/4,800) = 
$9.00




a (intercept)
684.65
b coefficient
7.2884
Standard error of the estimate34.469
R-squared
0.99724
t-value for b
60.105





Data regarding the maintenance hours and costs for the last year and the results of the regression analysisfollow:

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost management a strategic approach

ISBN: 978-0073526942

5th edition

Authors: Edward J. Blocher, David E. Stout, Gary Cokins

Question Posted: