Refer to TMCs project selection problem presented in this chapter. In the solution shown in Figure, The

Question:

Refer to TMC’s project selection problem presented in this chapter. In the solution shown in Figure, The probability of success for project 4 is only 0.3488. Thus, project 4 is almost twice as likely to fail as succeed if it is assigned only three engineers. As a result, management might want to add a constraint to this problem to ensure that if a project is selected, it must have at least a 50% chance of succeeding.

a. Reformulate TMC’s problem so that if a project is selected, it must have at least a 50% chance of succeeding.

b. Implement your model in a spreadsheet.

c. What is the optimalsolution?

Refer to TMC’s project selection problem presented in this chapt