The following data for Kitchen Tile Company relate to the production of 18,000 tiles during the past
Question:
The following data for Kitchen Tile Company relate to the production of 18,000 tiles during the past month. The company allocates fixed overhead costs at a standard rate of $19 per direct labour hour:
Direct labour:
Standard cost is 6 tiles per hour at $24.00 per hour
Actual cost per hour was $24.50
Labour efficiency variance was $6,720 F
Fixed overhead costs:
Estimated = $60,000
Actual = $58,720
Required:
A. How many actual labour hours were worked to produce the 18,000 tiles?
B. What is the price variance for direct labour?
C. What is the budget variance for fixed costs?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cost Management Measuring, Monitoring and Motivating Performance
ISBN: 978-1119185697
3rd Canadian edition
Authors: Leslie G. Eldenburg, Susan K. Wolcott, Liang Hsuan Chen, Gail Cook
Question Posted: