Three alternatives are being considered. Alternative A has a useful life of 5 years; Alternative B, 6

Question:

Three alternatives are being considered. Alternative A has a useful life of 5 years; Alternative B, 6 years; and Alternative C, 8 years. Using the least-common-multiple approach, what is the planning horizon?

a. 30 years

b. 48 years

c. 120 years

d. 240 years