Question:
In a job costing system, which of the following statements about materials is not correct?
a. A materials requisition is used to request materials needed from the storeroom.
b. Materials used during production are always classified as direct materials.
c. Materials that cannot be traced to a particular job are treated as manufacturing overhead.
d. The job cost record for a job will contain all direct material used for that particular job.