Review the three sample specifications highlighted in this chapter, and explain why project managers often fail to
Question:
Review the three sample specifications highlighted in this chapter, and explain why project managers often fail to prevent ambiguity, which would help avoid delay and prevent disputes and costly litigation. How would you have changed the language in these three specifications to avoid ambiguity and uncertainty?
A few selected provisions and the problems and risks these specifications presented at the Big Dig are highlighted in the three examples that follow.
Transcribed Image Text:
EXAMPLE 1: SPECIFICATION Section 4.04 Differing Site Conditions: If during the progress of the Work, the Contractor discovers that the actual subsurface conditions encountered at the site differ substantially or materially from those shown on the Plans or indicated in the Contract Documents, ... the contractor... may request an Equitable Adjustment in the Contract Price... Problem: Disputes arising from this specification were quite common due to the differing interpretations of "substantially or materially" and whether the designer should be liable for not identifying the subsurface conditions in the drawing or the owner should be liable because the contractor was not at fault. Solution: (1) the designer and the owner should work together to resolve any differences; (2) the meaning of "differ substantially or mate- rially" should be defined to a greater extent in the specification; (3) the method of calculating the equitable adjustment should be included in the contract documents; and (4) the risks and exposures should be iden- tified and included in the contractor's baseline, or through a construction contingency.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 66% (3 reviews)
The examples provided highlight common issues in project specifications that can lead to ambiguity disputes delays and litigation Heres an analysis of ...View the full answer
Answered By
Sandip Nandnawar
I am a B.E (Information technology) from GECA and also have an M.C.M from The University of RTMNU, MH.
I worked as a software developer (Programmer and TL). Also working as an expert for the last 6 years and deal with complex assessment and projects. I have a team and lead a team of experts and conducted primary and secondary research. I am a senior software engg and senior expert and deal with all types of CSE and IT and other IT-related assessments and projects and homework.
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Megaproject Management Lessons On Risk And Project Management From The Big Dig
ISBN: 9781118115473
1st Edition
Authors: Virginia A. Greiman
Question Posted:
Students also viewed these Business questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
1. With reference to John Kotters eight-stage model of change, what mistakes did BA make in this instance, and what aspects of the change management process did they handle well? 2. How can the...
-
Review the materials on privacy issues in this chapter and then log on to the website for an Internet vendor that you, or someone you know, has used. Can you find the vendors privacy policy? Is it...
-
The mid-day wind speed, in knots, at a coastal resort is normally distributed with mean 12.8 and standard deviation . a. Given that 15% of the recorded wind speeds are less than 10 knots, find the...
-
Scott Ginsburg was chief executive officer (CEO) of Evergreen Media Corp., which owned and operated radio stations. In 1996, Evergreen became interested in acquiring EZ Communications, Inc., which...
-
Magdalen, Miriam, and Mary June were asked to consider two different cash flows: $500 that they could receive today and $1000 that would be received 3 years from today. Magdalen wanted the $500...
-
What would happen to the SML graph in Figure 8.8 if expected inflation increased or decreased? Figure 8.8 268 269 270 271 272 273 274 275 A Required Rate of Return TH-13.0% SML: r, RF+RPM * b D E F H...
-
(Prepared from a situation suggested by Professor John W. Hardy.) Lone Star Meat Packers is a major processor of beef and other meat products. The company has a large amount of T-bone steak on hand,...
-
In some ways, a qualitative portfolio manager could never really be an index portfolio manager, whereas a quantitative portfolio manager could be. Explain why.
-
On a particular day, a random sample of 12 tins of peas was taken from the output of a canning factory, and their contents were weighed. The mean and standard deviation of weights (of the contents of...
-
What processes and procedures will you need to perform integrated change control?
-
What is the critical role of the project sponsor/owner (and the relative roles of sponsor, portfolio manager, and program manager in governing and managing projects)?
-
Consider the following sequence of year-end cash flows: What is the uniform annual equivalent if the interest rate is 12% per year? (a) $20,422 (b) $17,511 (c) $23,204 (d) $22,000 (e) $12,422 2 Cash...
-
Retained earnings, December 31, 2015 $ 307,600 Cost of equipment purchased during 2016 32,000 Net loss for the year ended December 31, 2016 4,600 Dividends declared and paid in 2016 13,500 Decrease...
-
A railway train is travelling through a long tunnel at a speed of 77 km/h and occupies 75% of the tunnel cross-section. The air within the tunnel as a whole is at rest. The barometric reading and the...
-
What federal advisory board recommends standards to the National Coordinator for Health IT? brief.
-
The Bureau of Reclamation plans to increase the height of Shasta Dam in Northern California by 18.5 ft. The current dam height is 600 ft. The stated increase in storage capacity will be 14%. The...
-
There are TWO bidders who have independent private values, v and v2. For Bidder 1, his value can be either $10 or $40, each with probability of 1/2. For Bidder 2, her value can be either $20 or $50,...
-
Waldum Company purchased packaging equipment on January 5, 2012, for $135,000. The equipment was expected to have a useful life of three years, or 18,000 operating hours, and a residual value of...
-
Q:1 Take any product or service offered in Pakistan and apply all determinents of customer Perceived value ?
-
Discuss how slower economic growth or no economic growth would affect your college communityin particular, its marketing institutions.
-
Explain in your own words how economists look at markets and arrive at the law of diminishing demand.
-
Explain what a demand curve is and why it is usually down-sloping. Then give an example of a product for which the demand curve might not be downsloping over some possible price ranges. Explain the...
-
(a) What are the main principles of (Markowitz) portfolio theory? How does the risk-free lending and borrowing extend the range of investment possibilities (in relation to the efficient portfolio on...
-
Determine the OTB or Overbought situation for October given the following: Stock on hand, October 1 = $122,000 Stock on order = $16,200 Planned BOM stock for November 1 = $124,000 Planned sales for...
-
(a) Emerald Industries has equity with a beta of 1.5. The company has just paid a dividend of 0.80 per share, and dividends are expected to grow at 5% each year. The expected return of the market is...
Study smarter with the SolutionInn App