Construct a Gantt chart for the project defined in Problem and Exercise 7. Problem and Exercise 7

Question:

Construct a Gantt chart for the project defined in Problem and Exercise 7.

Problem and Exercise 7

A project has been defined to contain the following list of activities along with their required times for completion.image text in transcribed

a. Draw a network diagram for the activities.

b. Calculate the earliest expected completion time.

c. Show the critical path.

d. What would happen if activity 6 were revised to take 6 weeks instead of 2 weeks?

Step by Step Answer:

Related Book For  answer-question

Modern Systems Analysis And Design

ISBN: 9780132991308

7th Edition

Authors: Jeffrey A Hoffer, Joey George, Joseph S Valacich

Question Posted: