Look again at the activities outlined in Problem and Exercise 3-40. Assume that your team is in

Question:

Look again at the activities outlined in Problem and Exercise 3-40. Assume that your team is in its first week of the project and has discovered that each of the activity duration estimates is wrong. Activity 2 will take only two weeks to complete. Activities 4 and 7 will each take three times longer than anticipated. All other activities will take twice as long to complete as previously estimated. In addition, a new activity, number 11, has been added. It will take one week to complete, and its immediate predecessors are activities 10 and 9. Adjust the network diagram and recalculate the earliest expected completion times.


Exercise 3-40

A project has been defined to contain the following list of activities along with their required times for completion.

Activity No. Immediate Activity Time (weeks) Predecessors 1. Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document 3 2 1 3 2 2 4 6 2 3 6 2 3,4 7 4 4,5 8 6,7 9. 7 7 10 Install 2


a. Draw a network diagram for the activities.

b. Calculate the earliest expected completion time.

c. Show the critical path.

d. What would happen if activity 6 were revised to take six weeks instead of two weeks?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Modern Systems Analysis And Design

ISBN: 9780134204925

8th Edition

Authors: Joseph Valacich, Joey George

Question Posted: