A sandwich manufacturing firm makes sandwich platters with 20 pieces per platter. Each platter takes 30 minutes

Question:

A sandwich manufacturing firm makes sandwich platters with 20 pieces per platter. Each platter takes 30 minutes to prepare and pack. After 12 platters, the surface is cleaned and sanitized, which requires a 1-hour changeover. The company operates 7.5 hour shifts, 3 shifts per day, 220 days per year. If the firm manufactures 7000 platters per year, what is its capacity cushion?