The BOM for product A is shown in Figure 11.40, and data from the inventory records are

Question:

The BOM for product A is shown in Figure 11.40, and data from the inventory records are shown in Table 11.9. In the MPS for product A, the MPS start row has 100 units in week 3 and 200 in week 6. Develop the material requirements plan for the next 6 weeks for items C, D, and E.
a. Develop the material requirements plan for the next 6 weeks for items C, D, and E.
b. What specific managerial actions are required in week 1?Data Category Lot-sizing rule Lead time Scheduled receipts Beginning inventory C L4L 2 weeks None 50 ITEM DA D (2) E (4)