The manager at Trams Candy Shop wants to determine a consecutive days off schedule for its workforce.

Question:

The manager at Tram€™s Candy Shop wants to determine a consecutive days off schedule for its workforce. Use the following daily worker requirement, and use part-time workers if needed.

м т Th Su F Requirement б 4 4 3 2 Answer: Th Su Requirement 6. 4 4 3. 2 Worker1 6 2 Worker 2 5 3 2 Worker 3 4 2 3 2 W

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: