The MPS start quantities for product A calls for the assembly department to begin final assembly according
Question:
The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule: 100 units in week 2; 200 units in week 4; 120 units in week 6; 180 units in week 7; and 60 units in week 8. Develop a material requirements plan for the next 8 weeks for items B, C, and D. The BOM for A is shown in Figure 11.26, and data from the inventory records are shown in Table 11.4.
Data from Figure 11.26:
Data from Table 11.4: