Activity slack (also known as float) can be calculated through which of the following means? a. Early

Question:

Activity slack (also known as float) can be calculated through which of the following means?

a. Early finish (EF) – late finish (LF)

b. Early finish (EF) – early start (ES)

c. Late finish (LF) – late start (LS)

d. Late start (LS) – early start (ES)