fixed-price contract is typically sought by the project manager from the customer's organization when: A. The risk

Question:

fixed-price contract is typically sought by the project manager from the customer's organization when:
A. The risk and consequences associated with the A A contracted task are large and the customer wishes to transfer the risk.
B. The project manager's company is proficient at dealing with the contracted activities.
C. Neither the contractor nor the project manager understand the scope of the task.
D. The project manager's company has excess production capacity.