If BAC = $12,000 and CPI = 1.2, what is the variance at completion? A. $2000 B.
Question:
If BAC = $12,000 and CPI = 1.2, what is the variance at completion?
A. –$2000
B. +$2000
C. –$3000
D. +$3000
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (1 review)
Answered By
Joseph Mwaura
I have been teaching college students in various subjects for 9 years now. Besides, I have been tutoring online with several tutoring companies from 2010 to date. The 9 years of experience as a tutor has enabled me to develop multiple tutoring skills and see thousands of students excel in their education and in life after school which gives me much pleasure. I have assisted students in essay writing and in doing academic research and this has helped me be well versed with the various writing styles such as APA, MLA, Chicago/ Turabian, Harvard. I am always ready to handle work at any hour and in any way as students specify. In my tutoring journey, excellence has always been my guiding standard.
4.00+
1+ Reviews
10+ Question Solved
Related Book For
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9781119805373
13th Edition
Authors: Harold Kerzner
Question Posted:
Students also viewed these Business questions
-
If BAC = $12,000 and CPI = 0.8, what is the variance at completion? A. $2000 B. +$2000 C. $3000 D. +$3000
-
You and your spouse have purchased a foreclosure you hope to flip for a profit. The two bathrooms had been recently remodeled by the previous owners. The three bedrooms need only cosmetic work -...
-
Homework-2 DECISION ANALYSIS PROBLEMS Problem-1: Kenneth Brown is the principal owner of Brown Oil, Inc. After quitting his university teaching job, Ken has been able to increase his annual salary by...
-
Do you consider the Internet message boards that Anjali wishes to use to be public or private? How would you justify your answer? Anjali, was in her final year of study for an undergraduate business...
-
Compute the payback period for each of these two separate investments (round the payback period to two decimals): a. A new operating system for an existing machine is expected to cost $260,000 and...
-
What are the key issues in conducting structured interviews?
-
Discuss corporate tactics that can be used in a down economy to keep top talent.
-
PepsiCos financial statements are presented in Appendix A. Financial statements of The Coca-Cola Company are presented in Appendix B. Instructions (a) Based on the information contained in the...
-
Find the sum of the geometric series, if possible. 9 1)5(2)" n=1 34 8 T 2) n=
-
If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is: A. 40 percent complete B. 80 percent complete C. 100 percent complete D. 120 percent complete
-
If BAC = $20,000 and the project is 40 percent complete, what is the earned value? A. $5000 B. $8000 C. $20,000 D. It cannot be determined.
-
List and describe two rapid-onset disasters. List and describe one slow onset disaster.
-
Why are confirmed letters of credit an effective hedge against country risk?
-
Why is China accumulating forex reserves so rapidly? Is its balance of payments indeed balancing?
-
Explain how letters of credit are used for international trade financing purposes.
-
What are letters of credit? Distinguish between revocable and irrevocable letters of credit.
-
What is different about gauging the credit risk of a foreign buyer?
-
If you know a company has a current ratio of 2 to 1, why is that not enough information to judge its liquidity?
-
A summary of changes in Pen Corporation's Investment in Sam account from January 1, 2011, to December 31, 2013, follows (in thousands): ADDITIONAL INFORMATION 1. Pen acquired its 80 percent interest...
-
Some executives would prefer to have their project managers become tunnel-vision workaholics, with the project managers falling in love with their jobs and living to work instead of working to live....
-
Project management is designed to make effective and efficient use of resources. Most companies that adopt project management find it easier to underemploy and schedule overtime than to overemploy...
-
The director of engineering services of R. P. Corporation believes that a project organizational structure of some sort would help resolve several of his problems. As part of the discussion, the...
-
Find the cost function for the marginal cost function. C'(x)=0.04e0.01x fixed cost is $9 C(x) =
-
Find dy dx for the following: x2 y2 4x 6y 12 x2 4 y2 16 1 x3 y x Find for each of the following cases: exy sin(x) 0 ln(xy) 2y 0 ln(y) ln(x 1) ln(x2) cos(x2 y) 2xy 0 x
-
a. X+ = 0.5X7-1 -0.20 Xt-2 + et = t- - b. X+ = ut + 0.5ut-1 -0.2ut-2 Ut = Calculate the first three lags of the theoretical ACFs implied by the following processes:
Accounting For Success The Guide To Short Case Resolution 3rd Edition - ISBN: 1928067050 - Free Book
Study smarter with the SolutionInn App