If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is: A. Ahead of
Question:
If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is:
A. Ahead of schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and over budget
D. Behind schedule and under budget